Purchase order vs invoice: what differs, field by field
A purchase order (PO) is written by the buyer, before delivery, to say what it will buy and at what price. An invoice is written by the supplier, after delivery, to ask to be paid. They describe the same purchase from two sides, so most of their lines should agree, and the differences are where accounts payable (AP) looks first. Below: a comparison table, the fields that must match and those that differ by design, a real PO and its invoice side by side, and the cases where there is no PO at all.

Purchase order vs invoice: the short answer
The difference between a purchase order and an invoice comes down to who writes it and when. The buyer issues the PO at the start of the transaction. The seller issues the invoice at the end. The PO commits the buyer to a purchase; the invoice states what is now owed. One moves no money, the other triggers the payment.
So no, a purchase order is not the same as an invoice, even when the two look alike on paper. They carry the same items, often the same quantities and prices, and the same PO number. That overlap is the point: the PO is the reference the invoice is checked against before anyone pays it.
| Purchase order | Invoice | |
|---|---|---|
| Written by | The buyer | The seller (supplier, vendor) |
| Sent | Before delivery | After delivery, or after the service is performed |
| Says | We will buy this, at this price, on these terms | You owe this amount, by this date |
| Reference number | PO number, set by the buyer | Invoice number, set by the seller, plus the buyer's PO number |
| Legal role | An offer to buy; a contract once the supplier accepts it | A demand for payment under that contract; in VAT countries, the document that supports the VAT claim |
| Accounting effect for the buyer | None in the ledger: a commitment against budget | A liability in accounts payable, then a payment |
| Who checks it | Purchasing approves it before it is sent | AP checks it against the PO and the goods receipt before payment |
| Can it be changed? | Yes, by a PO amendment (change order) | No: a mistake is corrected by a credit note and a new invoice |
In accounting software built for small businesses, a supplier invoice is often called a bill. The words describe the same document from two points of view: the supplier sends an invoice, the buyer records a bill. Either way, it is the request for payment, and the PO is what it should agree with.
What comes first, the PO or the invoice?
In a normal purchase, the PO always comes first. The sequence is the same in nearly every company, whatever the ERP:
- Requisition. Someone inside the buyer's company asks for a purchase and a manager approves it.
- Purchase order. Purchasing writes the PO, with its number, lines, prices and terms, and sends it to the supplier.
- Acceptance. The supplier confirms the order, or simply ships it, and records it as a sales order on its side (our guide on sales order vs purchase order puts the two documents side by side).
- Delivery and receipt. The goods arrive with a delivery note; the buyer's receiving team records what was counted.
- Invoice. The supplier invoices what it shipped, quoting the PO number.
- Check and payment. AP compares the invoice with the PO and the receipt, then pays on the due date.
Two exceptions are common. A supplier can ask for payment up front with a proforma invoice: a quote laid out like an invoice, sent before the order to state the price, often used for prepayment or customs. It is not a demand for payment of a delivered sale, and the final invoice follows later. The other exception is the PO raised *after* the invoice has arrived, to regularize a purchase someone made without one. Auditors call it an after the fact PO; it defeats the purpose of the control, because the price was never approved before the commitment.
What is a purchase order invoice?
The phrase "purchase order invoice" usually means an invoice issued against a PO: a supplier invoice that quotes the buyer's purchase order number, so AP can find the order and check the bill against it. People also call it a PO invoice or a PO backed invoice. The opposite is a non PO invoice, for spend that never had an order: utilities, rent, subscriptions, a one off repair.
The distinction matters inside AP because the two follow different paths. A PO invoice can be checked automatically, line by line, against data that already exists. A non PO invoice has nothing to be compared with, so it goes to a person, usually the budget owner, for approval. Many companies require a PO above a set amount precisely to keep that manual queue short.
If you need the basics of the order document itself, our guide to the purchase order meaning covers its fields and its four types.
Which fields must match, and which differ by design
A PO and its invoice share most of their content. AP does not check that they are identical; it checks that the fields that should agree do, and that the fields that may differ do so for a reason. The table below is the checklist most AP teams apply, whether a person runs it or software does.
| Field | On the PO | On the invoice | What AP expects |
|---|---|---|---|
| Document number | PO number | Invoice number, plus the PO number | Different numbers; the PO number on the invoice must be the right one |
| Dates | PO date, requested delivery date | Invoice date, often a supply date | Invoice dated on or after delivery |
| Parties | Buyer, bill to and ship to addresses, supplier | Supplier (with tax ID), buyer | Same legal entities on both |
| Item code and description | Buyer's item code or the supplier's SKU | Usually the supplier's SKU | Same item; codes mapped when they differ |
| Quantity and unit of measure (UoM) | Quantity ordered | Quantity shipped and billed | Equal or lower (partial shipment); never higher without an amended PO |
| Unit price | Agreed price | Billed price | Equal, or within a tolerance the company has set |
| Line amount | Quantity × price ordered | Quantity × price billed | Recomputed, not trusted as printed |
| Freight and charges | Agreed shipping, if any | Freight, fees, surcharges | Only charges the PO allows |
| Tax | Often estimated or left out | Actual tax, by rate | Recomputed from the lines; can legitimately differ from the PO estimate |
| Payment terms | For example Net 30 | Due date | Due date consistent with the PO terms |
| Bank details | Absent | Supplier's account | Unchanged from the vendor master; a new account is checked by phone before paying |
The quantity the invoice should be compared with is the quantity received, not only the quantity ordered. Comparing the invoice with the PO alone is two way matching; adding the receipt is the check described in our guide to 3 way matching in accounts payable.
A purchase order and its invoice, side by side
Here is a real calculation on an invented case. The PO is the specimen from our purchase order guide: PO NDC-2026-0418 from Northfield Dental Clinics to Brightline Medical Supply, four lines, total $867.00, payment Net 30. Eight days later the supplier ships and invoices. Receiving counted 38 boxes of gloves instead of 40; two were backordered.
| Line | Item | PO qty × price | PO amount | Invoice qty × price | Invoice amount |
|---|---|---|---|---|---|
| 1 | NG-100-M nitrile gloves, box of 100 | 40 × 7.85 | 314.00 | 38 × 7.85 | 298.30 |
| 2 | SY-3ML syringes 3 ml, box of 100 | 12 × 11.40 | 136.80 | 12 × 11.90 | 142.80 |
| 3 | GZ-4X4 gauze sponges, pack of 200 | 25 × 6.20 | 155.00 | 25 × 6.20 | 155.00 |
| 4 | DW-160 disinfectant wipes | 30 × 5.95 | 178.50 | 30 × 5.95 | 178.50 |
| Subtotal | 784.30 | 774.60 | |||
| Shipping | 18.00 | 18.00 | |||
| Sales tax 8.25 % on goods | 64.70 | 63.90 | |||
| Total | 867.00 | 856.50 |
Read only the totals and the invoice looks fine: $856.50 against an approved $867.00, $10.50 under the PO. Many companies would pay it, because a total below the commitment raises no flag.
Read the lines and two things appear. Line 1 bills 38 boxes, which matches what was received: that difference is legitimate, and the 2 boxes stay open on the PO. Line 2 bills the syringes at $11.90 instead of the agreed $11.40, an increase of $0.50 on 12 boxes. Nobody approved that price.
What should be paid: the goods at PO prices for the quantities received, 298.30 + 136.80 + 155.00 + 178.50 = $768.60; tax at 8.25 %, $63.41; shipping $18.00; total $850.01. The invoice is overbilled by $6.49: $6.00 of price and $0.49 of tax on that price. Small on one invoice, but a price that slips through once tends to stay on every invoice that follows. The usual outcome is a short hold on the invoice and a request for a credit note of $6.49, or for a corrected invoice.
The lesson is the one every AP team learns early: the total of an invoice tells you almost nothing. The comparison has to happen line by line, with quantity, unit and price as separate values. That is the job of PO matching, whether it runs in an AP suite, in an ERP or in a spreadsheet.
Is a purchase order legally binding like an invoice?
They bind in different ways. A PO is, in most cases, an offer to buy. Once the supplier accepts it, by confirming or by shipping, it becomes the contract for that sale. In the United States, sales of goods between businesses follow Article 2 of the Uniform Commercial Code, which allows acceptance "in any manner and by any medium reasonable", including prompt shipment (UCC § 2-206). Other countries have their own contract law, with similar outcomes in everyday trade.
An invoice does not create the obligation; it calls for payment under an agreement that already exists. Its legal weight is elsewhere: tax and record keeping. Governments set what an invoice must contain. In the United Kingdom, for example, an invoice must show a unique identification number, the supplier's and the customer's names and addresses, a description of what is charged, the supply date, the invoice date, the amounts, any VAT and the total owed. In VAT countries, the buyer's right to reclaim VAT generally rests on holding a valid VAT invoice, not on the PO.
The practical consequence: when the two disagree, the accepted PO is the evidence of what was agreed, and the invoice is what has to be corrected. That is why a supplier cannot "amend" an invoice by editing it. It issues a credit note that cancels all or part of the original, then a new invoice.
Do you need both a purchase order and an invoice?
A seller always needs an invoice to be paid and to account for the sale. A buyer does not always need a PO. Most companies set rules like these:
- PO required above an amount (for example $1,000 or $5,000), for all inventory and production materials, and for any new supplier.
- No PO for small, recurring or contractual spend: utilities, rent, insurance, software subscriptions, professional fees billed under an engagement letter.
- A blanket purchase order for repeated purchases from one supplier over a year, so each invoice is checked against the remaining balance rather than against a new order.
The cost of skipping the PO shows up in AP, not in purchasing. Every non PO invoice needs a person to confirm that the spend was approved and that the price is right. Every PO invoice can be checked against data, as in the example above.
Reading POs and invoices without retyping them
The checks above only work if the lines of both documents exist as data. When POs and invoices arrive as PDFs, scans, faxes or handwritten forms, someone retypes them first, and that is where most of the errors in the example come from: a price keyed from memory, a quantity typed from the wrong line.
Koncile, the company behind this site, reads both documents and returns the header and each line as separate fields (item code, description, quantity, unit, unit price, amount), with a confidence score on each value and the PO number that ties the invoice to its order. It does not create POs, approve invoices or pay them, and where the line comparison and its tolerances run, in Koncile or in your ERP after export, depends on your setup. An account comes with 20 free credits.
Frequently asked questions
01What is the main difference between a purchase order and an invoice?
The buyer issues the purchase order before delivery to commit to a purchase. The seller issues the invoice after delivery to request payment. The PO says what will be bought; the invoice says what is owed.
02Is a purchase order the same as an invoice?
No. They describe the same purchase and share the PO number, items and prices, but a PO is an order and creates no debt, while an invoice is a request for payment and creates a liability in accounts payable.
03What comes first, the PO or the invoice?
The PO. The buyer sends it, the supplier ships, then invoices with the PO number. The exceptions are a proforma invoice for prepayment and a PO raised after the invoice to regularize a purchase, which auditors treat as a control failure.
04How is a purchase order different from a bill?
A bill is the supplier invoice as the buyer records it. The PO is issued by the buyer before delivery; the bill comes from the supplier afterwards and should agree with the PO on items and prices.
05What happens after a PO is issued?
The supplier accepts it, records it as a sales order and ships. The buyer records the goods receipt. The supplier invoices, and AP checks the invoice against the PO and the receipt before paying on the agreed terms.
06Is a sales order the same thing as an invoice?
No. A sales order is the supplier's internal record of the customer's PO, created when the order is accepted. The invoice is sent to the customer after shipment to ask for payment.
07Can an invoice be higher than the purchase order?
Only within a tolerance the buyer has set, or after an amended PO. Otherwise the invoice is held and the supplier is asked for a credit note or a corrected invoice.
08What is a non PO invoice?
An invoice for spend that had no purchase order, such as utilities, rent or subscriptions. It cannot be matched automatically, so a budget owner approves it manually before payment.
Sources
- UCC § 2-206, Offer and acceptance in formation of contract, Legal Information Institute, Cornell Law School (read on 4 November 2026).
- Invoicing and taking payment from customers: what invoices must include, GOV.UK (read on 5 November 2026).
- Koncile API documentation: format of the extraction response.
Put a PO and its invoice side by side
Upload a purchase order and the invoice that bills it, and get every line of both back as fields you can compare. No card, no call.
Create a Koncile account, 20 free creditsTalk to an expert
20 free credits, no credit card. For professional use only.